Additional Traffic Management Arrangements as of 9 November 2020
Please find below a summary of additional traffic management arrangements to accommodate site investigations works and utility diversions outside the main area of works.
Traffic management arrangements for the main area of works are available to view and download.
Leith Walk
McDonald Road/Leith Walk junction - Road Closure - NOW REOPENED TO ONE-WAY TRAFFIC
McDonald Road will be opening up to one-way traffic from Wednesday 4 November. The one lane will enable access from McDonald Road onto Leith Walk and Brunswick Street.
View more information on McDonald Road/Leith Walk junction
McDonald Road/Broughton Road junction - Changes to Traffic Management Arrangements
We will be installing a set of 3 way lights at the McDonald Road/Broughton Road junction, creating 2 extra pedestrian crossings. This will also be implemented on Thursday 4 November.
Shrub Place - Pedestrian Walkway
Changes have been implemented to the pedestrian walkway in the Shrubhill area on the west side of Leith Walk. Please be aware of the new arrangements and note pedestrian access will be maintained. Access to and from properties of the Engine Yard developments underground carpark area will be maintained by the installation of a prioritised running lane between the carpark entrance and Shrub Place. This running lane will be clearly marked, whilst being segregated from both pedestrians and the adjacent cycle lane.
View the traffic management drawing for the Shrubhill area.
Iona Street - Temporary Road Closure - NOW REOPENED
Access to Leith Walk from Iona Street will be closed from Monday 9 November. Expected duration of this closure is 2 weeks. Localised Diversions will be in place and access is via Dalmeny Street.
Further information on Iona Street temporary road closure.
Jane Street and Arthur Street - Fence Line Adjustments on Footpath and Cycle Way
There will be minor adjustments to the fence line on Leith Walk at Jane Street and Arthur Street from Monday 16 November for 6 and 2 weeks respectively. This is to accommodate utility works on the footpath.
Foot of the Walk - Newhaven
Constitution Street access to Tower Street Industrial Estate - Road Closure
We will be carrying out road resurfacing works on the running lane at Tower Street Industrial Estate. To minimise the impact to the businesses in this area these works will be completed on Sunday 22 November. Works are expected to take approximately 3-4hrs and will commence at 12 midday. The access road to Tower Street Industrial Estate will be closed until approximately 7pm to allow the tar to cure.
View the Tower Street traffic management plan
FOTW – Laurie Street
Alternative footpath arrangements have been installed to accommodate works – pedestrian diversion signage is in place and access to properties will be maintained at all times.
Queen Charlotte Street - Temporary Traffic Lights
We will be installing temporary traffic lights and pedestrian crossings at the Queen Charlotte Street junction with Constriction Street to accommodate BT works. These will be in place form Wednesday 4 November for approximately 2 weeks. Parking restrictions will be in place to accommodate these works.
Download the Queen Charlotte Street traffic management plan (PDF)
Lindsay Road - Footpath Diversion and Temporary Bus Stop Relocation - RESCHEDULED Monday 9 November
We will be carrying out utility works at the Annfield Bus Stop on Lindsay Road. Footpath diversions will be in place and the bus stop will be temporary relocated further west towards the traffic lights. This will be in place from Monday 2 November for approximately 2 days. Please note, this has been rescheduled for Monday 9 November