Additional Traffic Management Arrangements as of 26 October 2020
Please find below a summary of additional traffic management arrangements to accommodate site investigations works and utility diversions outside the main area of works.
Traffic management arrangements for the main area of works are available to view and download.
Leith Walk
McDonald Road/Leith Walk junction - Road Closure
McDonald Road/Leith Walk junction remains closed to accommodate utility diversions.
Shrub Place - Pedestrian Walkway
Changes have been implemented to the pedestrian walkway in the Shrubhill area on the west side of Leith Walk. Please be aware of the new arrangements and note pedestrian access will be maintained. Access to and from properties of the Engine Yard developments underground carpark area will be maintained by the installation of a prioritised running lane between the carpark entrance and Shrub Place. This running lane will be clearly marked, whilst being segregated from both pedestrians and the adjacent cycle lane.
View the traffic management drawing for the Shrubhill area.
Iona Street - Temporary Road Closure
Access to Leith Walk from Iona Street will be closed from Monday 9 November. Expected duration of this closure is 2 weeks. Localised Diversions will be in place and access is via Dalmeny Street.
Further information on Iona Street temporary road closure.
Foot of the Walk - Newhaven
Foot of the Walk to Laurie Street - Footpath Closure - NOW REOPENED
Footpath closure from Foot of the Walk to Laurie Street on the east side has now reopened.
Mitchell Street to Assembly Street - Footpath Closure
Footpath closure on Constitution Street from Mitchell Street to Assembly Street on the east side to accommodate utility diversion works. Pedestrian diversions will be in place and access to properties will be maintained at all times.
Assembly Street - Footpath Closures
Access to Assembly Street is via Baltic Street to accommodate utility works. Pedestrian diversions are in place.
Queen Charlotte Street - Temporary Traffic Lights
We will be installing temporary traffic lights and pedestrian crossings at the Queen Charlotte Street junction with Constriction Street to accommodate BT works. These will be in place form Wednesday 4 November for approximately 2 weeks. Parking restrictions will be in place to accommodate these works.
Download the Queen Charlotte Street traffic management plan (PDF)
Lindsay Road - Footpath Diversion and Temporary Bus Stop Relocation
We will be carrying out utility works at the Annfield Bus Stop on Lindsay Road. Footpath diversions will be in place and the bus stop will be temporary relocated further west towards the traffic lights. This will be in place from Monday 2 November for approximately 2 days.