Сòòò½APP

Are you a resident or business in the local area? Join our mailing lists

Notification of extension of work site at CALA Developments

More details of the extension of our work site opposite the CALA Developments.

The section to the north of Ocean Terminal to CALA Development remains open to traffic. However, from Monday 23 August there will be 3-way temporary traffic lights installed to facilitate additional works. Vehicle access will be maintained and managed via 3-way temporary traffic management arrangements with a pedestrian diversion also in place. 

These changes are to accommodate the extension of site that sits parallel to the CALA Developments. In order to mobilise the site extension enabling works are required. These include: 

  • Installation of the new temporary running lane. This will require residents to use the CALA Developments construction access points for a short duration on the morning of Wednesday 25 August. 
  • Closure of footway heading east bound, a diversion will be sign posted.
  • Realignment of the existing carriageway.
  • Removal of lampost.

Following these works, site will then be extended and excavation, utility works, main infrastructure and landscaping works will begin. These arrangements will be in place from Monday 23 August and are scheduled to be in place until early Spring 2022.  

View the new traffic management arrangements in the image below. 

Three way traffic lights will be installed opposite CALA Developments. This map shows the exact location of the lights.

 

Contact Us

If you have any concerns or further questions regarding these works then please contact the Trams to Newhaven project team by email on Newhaven.tram@edinburgh.gov.uk or alternatively contact our customer helpline on 0131 322 1122 (local rate Monday to Sunday 8am to 7pm).

Published: 16th August 2021